Sunday, 30 March 2014

The windows are in!

The custom made windows started going in on Friday in the two new lounges on Deck A. The new lounges are fully air-conditioned and offer superb panoramic views across the Solent and Southampton Water.

Here are some pics;






Thursday, 27 March 2014

New windows, new signage and new recycling station...

The first new hi-spec tinted windows were being installed tonight on the Red Falcon;


The new wayfinding signage has also started to be installed;


The new recycling station is also now complete;




Monday, 24 March 2014

Latest updates from the Falcon

Progress has been great in the last week with flooring complete in the new lounges, furniture going in, new servery equipment being installed and more, here's some pics;





Friday, 14 March 2014

Work is progressing fast...

It's been a good week for the Southampton based team working on the new look Red Falcon. Both lounges are now fully weatherproof (except for the windows, they'll be fitted last!), the interiors are starting to take shape and exterior paint prep has begun.

Paint prep on the exterior;




New flooring, ceilings and wall fittings are starting go in;


Air conditioning installed in all areas;


The start of the new look ReFuel;


Saturday, 8 March 2014

Some great progress this week..

This week we've seen some great progress with the Red Falcon refurbishments, here's some of the highlights;

The new ceiling and wall coverings have gone in on Deck B


The floor has been stripped and is being completely resurfaced this weekend. You can see an air-conditioning unit in here too.


Work has started on fitting out the 2 new lounges on Deck A - don't worry we won't having plywood windows!!




The lower exterior of the vessel is also getting ready for painting;


Tuesday, 4 March 2014

Last section of the roof goes on!

The new look Red Falcon project is going well. At the end of last week the last piece of the new lounge roof went on, here are some pics;